Courseiva
PRINCE2 ProcesseseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During the Initiating a Project process, the project manager is reviewing the Business Case. Which statement best describes the purpose of this review?

⚠ Common exam trap

Many exam-takers confuse the purpose of the Initiating a Project process with the Directing a Project process, mistakenly thinking that the Business Case review is for final approval rather than for developing and confirming viability.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To develop a detailed justification for the project and confirm it remains viable.

During the Initiating a Project process, the Business Case is reviewed to develop a detailed justification for the project and confirm it remains viable. This involves refining the outline Business Case from the Starting Up a Project process into a fully detailed document that justifies the project's continued existence based on costs, benefits, risks, and timescales. The review ensures the project is still aligned with corporate objectives and that the investment is worthwhile before proceeding to the next stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To confirm the project's scope and high-level risks before the project mandate is issued.

    Why it's wrong here

    This occurs during Starting Up a Project, not Initiating a Project.

  • To authorize work packages for the first stage of the project.

    Why it's wrong here

    Authorizing work packages happens during Managing a Stage Boundary or Controlling a Stage.

  • To develop a detailed justification for the project and confirm it remains viable.

    Why this is correct

    Initiating a Project refines the Business Case to ensure the project is worthwhile.

  • To obtain final approval from the project board before project execution begins.

    Why it's wrong here

    Approval is obtained at the end of Initiating a Project, but the review is to ensure viability.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.