PRINCE2F PRINCE2 Processes Practice Question
A Team Manager completes a Work Package and requests formal acceptance of the product. Which process handles this?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Managing Product Delivery
Managing Product Delivery is the process where the Team Manager executes the work and delivers completed products to the Project Manager for acceptance. Controlling a Stage is the PM's process for managing the stage; Managing a Stage Boundary focuses on stage end and next stage planning; Closing a Project handles final project closure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Managing a Stage Boundary
Why it's wrong here
SB plans the next stage and reports on the current stage, not product delivery.
- ✓
Managing Product Delivery
Why this is correct
MP includes delivering the completed product and obtaining acceptance.
- ✗
Closing a Project
Why it's wrong here
CP handles final project closure, not delivery of individual products.
- ✗
Controlling a Stage
Why it's wrong here
CS is the PM's process; acceptance of products from the Team Manager occurs in MP.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.