PRINCE2F People: organizations, teams, and leadership Practice Question
In PRINCE2, who is responsible for preparing and updating the Highlight Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager prepares the Highlight Report and sends it to the Project Board at regular intervals (e.g., weekly or monthly) to provide a summary of stage status.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team Manager
Why it's wrong here
The Team Manager produces Checkpoint Reports, not Highlight Reports.
- ✗
Project Support
Why it's wrong here
Project Support may assist but is not responsible for the Highlight Report.
- ✓
Project Manager
Why this is correct
The Project Manager is responsible for the Highlight Report.
- ✗
Senior User
Why it's wrong here
The Senior User is a Project Board member and receives the report, not produces it.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.