Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

⚠ Common exam trap

PeopleCert often tests the misconception that the Project Manager can handle tolerance breaches independently, but PRINCE2 strictly requires escalation to the Project Board via an Exception Report when any tolerance is forecast to be exceeded.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction

In PRINCE2, when a project is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is because the Project Manager does not have authority to exceed tolerances; the Project Board must decide whether to approve a revised Business Case, adjust tolerances, or terminate the project. Option C correctly follows the PRINCE2 principle of management by exception.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Close the project immediately as the Business Case is no longer viable

    Why it's wrong here

    The Business Case may still be viable; the Board decides.

  • Continue and report the cost overrun in the next Highlight Report

    Why it's wrong here

    Continuing without escalation violates management by exception.

  • Raise an Exception Report to the Project Board and await their direction

    Why this is correct

    Escalation via Exception Report is the correct response.

  • Increase the project budget to absorb the additional cost

    Why it's wrong here

    The PM cannot unilaterally increase the budget; that requires Project Board approval.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.