In PRINCE2, who is responsible for project assurance?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Project Board
Project assurance is the responsibility of the Project Board, which provides independent assurance.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Project Manager
Why it's wrong here
The Project Manager manages day-to-day delivery and cannot independently assure their own work; assurance is delegated by the Project Board to business, user and supplier assurance roles. The Project Manager is tempting because they monitor progress and controls, but that is management, not the independent verification of the project's viability that assurance requires.
- ✗
The Senior Supplier
Why it's wrong here
The Senior Supplier represents supplier interests on the Project Board and provides supplier resources; project assurance is delegated by the Project Board to assurance roles independent of the project manager. The Senior Supplier would be the right answer for supplying products, not for assuring the project.
- ✗
The Project Support
Why it's wrong here
Project Support provides administrative help and tool expertise, not assurance. Assurance requires independent monitoring of the project's viability, delegated by the Project Board to business, user or supplier assurance roles. Project Support is tempting because it sits close to the Project Manager and handles documentation, but it lacks the mandated independence from the project team that assurance demands.
- ✓
The Project Board
Why this is correct
Project assurance in PRINCE2 sits with the Project Board, which is accountable for confirming the project remains viable and aligned with business justification. Board members independently monitor each project management level, ensuring the three stakeholder interests are represented throughout.
About these practice questions
This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.