PRINCE2 Practices →easyMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

In PRINCE2, who is responsible for project assurance?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Project Board

Project assurance is the responsibility of the Project Board, which provides independent assurance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Project Manager

    Why it's wrong here

    The Project Manager manages day-to-day delivery and cannot independently assure their own work; assurance is delegated by the Project Board to business, user and supplier assurance roles. The Project Manager is tempting because they monitor progress and controls, but that is management, not the independent verification of the project's viability that assurance requires.

  • ✗

    The Senior Supplier

    Why it's wrong here

    The Senior Supplier represents supplier interests on the Project Board and provides supplier resources; project assurance is delegated by the Project Board to assurance roles independent of the project manager. The Senior Supplier would be the right answer for supplying products, not for assuring the project.

  • ✗

    The Project Support

    Why it's wrong here

    Project Support provides administrative help and tool expertise, not assurance. Assurance requires independent monitoring of the project's viability, delegated by the Project Board to business, user or supplier assurance roles. Project Support is tempting because it sits close to the Project Manager and handles documentation, but it lacks the mandated independence from the project team that assurance demands.

  • ✓

    The Project Board

    Why this is correct

    Project assurance in PRINCE2 sits with the Project Board, which is accountable for confirming the project remains viable and aligned with business justification. Board members independently monitor each project management level, ensuring the three stakeholder interests are represented throughout.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.