Checkpoint Report

The Checkpoint Report is a progress report prepared by the Team Manager and sent to the Project Manager at regular intervals. Option A is incorrect because the End Stage Report is prepared by the Project Manager for the Project Board at the end of each stage. Option B is incorrect because the Exception Report is prepared by the Project Manager when tolerances are forecast to be exceeded. Option C is incorrect because the Highlight Report is prepared by the Project Manager for the Project Board at regular intervals.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • End Stage Report

    Why it's wrong here

    The End Stage Report is prepared by the Project Manager at stage boundaries.

  • Exception Report

    Why it's wrong here

    The Exception Report is prepared when tolerances are forecast to be exceeded.

  • Highlight Report

    Why it's wrong here

    The Highlight Report goes from the Project Manager to the Project Board.

  • Checkpoint Report

    Why this is correct

    The Checkpoint Report provides progress information from the Team Manager to the Project Manager.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which report is produced by the Team Manager and sent to the Project Manager on a regular basis?

medium
  • A.Checkpoint Report
  • B.Highlight Report
  • C.End Stage Report
  • D.Exception Report

Why A: The Checkpoint Report is produced by the Team Manager and sent to the Project Manager to report progress at the work package level.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.