PRINCE2F PRINCE2 Practices Practice Question
Which report is prepared by the Team Manager and sent to the Project Manager at regular intervals?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Checkpoint Report
The Checkpoint Report is a progress report prepared by the Team Manager and sent to the Project Manager at regular intervals. Option A is incorrect because the End Stage Report is prepared by the Project Manager for the Project Board at the end of each stage. Option B is incorrect because the Exception Report is prepared by the Project Manager when tolerances are forecast to be exceeded. Option C is incorrect because the Highlight Report is prepared by the Project Manager for the Project Board at regular intervals.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
End Stage Report
Why it's wrong here
The End Stage Report is prepared by the Project Manager at stage boundaries.
- ✗
Exception Report
Why it's wrong here
The Exception Report is prepared when tolerances are forecast to be exceeded.
- ✗
Highlight Report
Why it's wrong here
The Highlight Report goes from the Project Manager to the Project Board.
- ✓
Checkpoint Report
Why this is correct
The Checkpoint Report provides progress information from the Team Manager to the Project Manager.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which report is produced by the Team Manager and sent to the Project Manager on a regular basis?
medium- ✓ A.Checkpoint Report
- B.Highlight Report
- C.End Stage Report
- D.Exception Report
Why A: The Checkpoint Report is produced by the Team Manager and sent to the Project Manager to report progress at the work package level.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.