Which THREE activities are part of the Controlling a Stage process?

⚠ Common exam trap

PRINCE2F often tests the confusion between Controlling a Stage and Managing a Stage Boundary, tricking candidates into selecting activities like approving the next Stage Plan or producing the PID that belong to other processes.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Authorize Work Packages

In PRINCE2, the Controlling a Stage process covers the day-to-day management of a stage by the Project Manager, and it includes authorizing work packages (option A) so that agreed work is formally delegated to Team Managers with the required tolerances and interfaces. It also includes reviewing progress and updating stage status (option C), which is done through regular checkpoint and highlight reports, comparing actuals against the Stage Plan and Work Package tolerances. Escalating issues and risks that exceed stage tolerances (option E) is also part of Controlling a Stage, since the Project Manager must raise an Exception Report to the Project Board when stage-level tolerances are forecast to be breached. Producing the Project Initiation Documentation (option B) belongs to Initiating a Project, and approving the next Stage Plan (option D) is a Project Board activity in Managing a Stage Boundary, so neither is part of Controlling a Stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Authorize Work Packages

    Why this is correct

    Authorising Work Packages sits within Controlling a Stage, where the Project Manager approves delegated work and confirms the Work Package's tolerances before the Team Manager begins delivery. This satisfies the stem's requirement for a Controlling a Stage activity, since authorisation occurs after stage authorisation and before progress monitoring.

  • ✗

    Produce the Project Initiation Documentation (PID)

    Why it's wrong here

    The PID is produced during Initiating a Project, not Controlling a Stage, which covers work package authorisation, progress monitoring, risk and issue management, and stage boundary reporting. It would be correct as an Initiating a Project activity, where the project's baseline documentation is assembled before delivery begins.

  • ✓

    Review progress and update stage status

    Why this is correct

    Reviewing progress and updating stage status is a Controlling a Stage activity, where the Project Manager monitors actuals against the Stage Plan, updates the Stage Status Summary, and reports progress to the Project Board within stage tolerances.

  • ✗

    Approve the next Stage Plan

    Why it's wrong here

    Approving the next Stage Plan belongs to the Managing a Stage Boundary process, which prepares the plan and updates the Business Case before the current stage ends. In the Controlling a Stage process, the focus is on monitoring work packages, reviewing issues and risks, and reporting progress—not authorising future stages. This option tempts because approving a plan seems like a natural control activity, but it is actually the trigger that moves the project into the next stage, not a task performed during the current stage’s day-to-day management.

  • ✓

    Escalate issues and risks that exceed stage tolerances

    Why this is correct

    Escalating issues and risks that exceed stage tolerances belongs to Controlling a Stage, where the Project Manager monitors the stage against its tolerances and refers breaches upward to the Project Board. This satisfies the stem's requirement for a Controlling a Stage activity, since tolerance breaches trigger exception escalation rather than being handled within the stage.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.