Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A project is in the Closing a Project process. What should the Project Manager produce to recommend project closure?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

End Project Report

The Project Manager produces an End Project Report and a Lessons Report, and then recommends closure to the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Exception Report

    Why it's wrong here

    Exception Report is for tolerance breaches.

  • End Project Report

    Why this is correct

    The End Project Report is the key output that summarizes the project and recommends closure.

  • End Stage Report

    Why it's wrong here

    End Stage Report is for the end of a stage, not the end of the project.

  • Project Brief

    Why it's wrong here

    Project Brief is from SU.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.