PRINCE2F PRINCE2 Processes Practice Question
A project is in the Closing a Project process. What should the Project Manager produce to recommend project closure?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
End Project Report
The Project Manager produces an End Project Report and a Lessons Report, and then recommends closure to the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Exception Report
Why it's wrong here
Exception Report is for tolerance breaches.
- ✓
End Project Report
Why this is correct
The End Project Report is the key output that summarizes the project and recommends closure.
- ✗
End Stage Report
Why it's wrong here
End Stage Report is for the end of a stage, not the end of the project.
- ✗
Project Brief
Why it's wrong here
Project Brief is from SU.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.