The Project Board has received an Exception Report from the Project Manager. What is the Project Board's next step?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Request an Exception Plan to assess options
When the Project Board receives an Exception Report, they typically request an Exception Plan to evaluate options. They then decide whether to approve the plan, which may involve changes to the project. A new Project Plan may be part of the Exception Plan, but the immediate step is to request the plan.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.