The Project Board has received an Exception Report from the Project Manager. What is the Project Board's next step?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Request an Exception Plan to assess options

When the Project Board receives an Exception Report, they typically request an Exception Plan to evaluate options. They then decide whether to approve the plan, which may involve changes to the project. A new Project Plan may be part of the Exception Plan, but the immediate step is to request the plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Approve the Exception Report

    Why it's wrong here

    Approving the report is not the Board's decision; an Exception Report requests a tolerances decision, so the Board must direct corrective action or escalate. Approval suits routine progress reports within tolerance, where no exception exists and the Project Manager retains authority.

  • ✗

    Request a new Project Plan

    Why it's wrong here

    Requesting a new Project Plan is a Project Manager activity; the Board does not author plans. The Board's role on receiving an Exception Report is to make a decision — approve, reject or request changes to the Exception Plan — within the tolerances delegated to it.

  • ✓

    Request an Exception Plan to assess options

    Why this is correct

    An Exception Report shows the stage or project will exceed tolerance, so the Project Board requests an Exception Plan describing the options and their implications. The Board then decides whether to approve, amend or stop the project.

  • ✗

    Close the project

    Why it's wrong here

    Closing the project only follows premature termination or a completed final stage, neither indicated here. The Board must first decide how to respond to the exception, such as requesting a plan or granting a tolerance. Closure would be correct if the business case had collapsed entirely.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.