In the Directing a Project process, which of the following is a key responsibility of the Project Board?

⚠ Common exam trap

PeopleCert often tests the distinction between the Project Board's strategic control (authorizing stages) and the Project Manager's tactical execution (producing reports, managing daily work), leading candidates to confuse the two roles.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Authorizing the next Stage Plan

In PRINCE2, the Directing a Project process is the decision-making layer where the Project Board exercises overall control. A key responsibility is authorizing the next Stage Plan, which formally approves the detailed plan for the upcoming management stage and commits the resources required to execute it. This ensures the project remains viable and aligned with business justification before proceeding.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Producing Highlight Reports

    Why it's wrong here

    Highlight Reports are produced by the Project Manager, not the Project Board, which only receives and reviews them at stage boundaries. It is tempting because the Board does consume this reporting to direct the project, so the artefact feels board-owned, but authoring sits with the Project Manager under Managing a Stage Boundary.

  • ✓

    Authorizing the next Stage Plan

    Why this is correct

    Authorising the next Stage Plan sits with the Project Board because Directing a Project reserves stage-boundary decisions to that level, satisfying the stem's requirement for a Project Board responsibility. The Project Manager drafts the plan; the Board alone grants the authority to proceed, ensuring continued business justification before committing resources.

  • ✗

    Managing day-to-day work within a stage

    Why it's wrong here

    Day-to-day work within a stage belongs to the Project Manager, delegated through Work Packages; the Project Board directs by exception, authorising stage boundaries and tolerances. It tempts because board members do oversee delivery, but managing tasks is a management-layer activity, not a directing responsibility.

  • ✗

    Accepting Work Packages

    Why it's wrong here

    Accepting Work Packages is performed by the Project Manager when agreeing delivery with Team Managers, not by the Project Board, which authorises stages and project closure. It tempts because acceptance implies approval authority, yet the board's approvals concern stage and project-level decisions.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.