PRINCE2F PRINCE2 Practices Practice Question
Which TWO of the following are components of the Business Case?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Expected benefits
The Business Case includes expected benefits, costs, timescales, major risks, etc. Options, investment appraisal, and dis-benefits are also components.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Plan
Why it's wrong here
The Project Plan is separate, though related.
- ✓
Expected benefits
Why this is correct
Benefits are a key component.
- ✗
Product Breakdown Structure
Why it's wrong here
This is a planning tool, not part of the Business Case.
- ✗
Quality Register
Why it's wrong here
The Quality Register is for quality management.
- ✓
Major risks
Why this is correct
Major risks are included.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.