Initiating a Project
The Project Plan is created during Initiating a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Initiating a Project
Why this is correct
IP produces the PID, which includes the Project Plan.
- ✗
Managing a Stage Boundary
Why it's wrong here
This updates the Project Plan but does not create it.
- ✗
Starting Up a Project
Why it's wrong here
SU produces the Project Brief, not the Project Plan.
- ✗
Directing a Project
Why it's wrong here
DP is for decision-making, not planning.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.