During the Managing a Stage Boundary process, the Project Manager reviews the Business Case and finds that the expected benefits are no longer achievable. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Recommend to the Project Board that the project should be closed as the Business Case is no longer viable

If the Business Case is no longer viable, the Project Manager should recommend to the Project Board that the project should be closed. The Project Board makes the final decision, not the Project Manager. Option A is incorrect because an Exception Plan is for handling tolerance deviations, not for a failed Business Case. Option B is incorrect because continuing as planned would ignore the loss of viability. Option D is incorrect because the Project Manager cannot unilaterally close the project; the Board must decide.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Create an Exception Plan to revise the benefits

    Why it's wrong here

    Exception Plans address tolerance deviations; a failed Business Case requires Board decision.

  • Continue with the next stage as planned and report the issue in the End Project Report

    Why it's wrong here

    Continuing with an unviable Business Case is not permitted; the issue must be escalated.

  • Recommend to the Project Board that the project should be closed as the Business Case is no longer viable

    Why this is correct

    The Project Manager should escalate to the Project Board, which may decide to close the project.

  • Close the project immediately without consulting the Project Board

    Why it's wrong here

    Only the Project Board can authorize premature closure.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.