Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Who receives Highlight Reports?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board

Highlight Reports are prepared by the Project Manager and sent to the Project Board (and possibly stakeholders) at regular intervals.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Board

    Why this is correct

    The Project Board receives Highlight Reports from the Project Manager.

  • Senior Supplier

    Why it's wrong here

    Senior Supplier is part of the Project Board, but the board as a whole receives Highlight Reports.

  • Project Support

    Why it's wrong here

    Project Support may assist in preparation but is not the recipient.

  • Team Manager

    Why it's wrong here

    Team Manager receives Checkpoint Reports from teams, not Highlight Reports.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.