Who receives Highlight Reports?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

Highlight Reports are prepared by the Project Manager and sent to the Project Board (and possibly stakeholders) at regular intervals.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Board

    Why this is correct

    The Project Board needs Highlight Reports to monitor progress, compare actuals against the plan, and make informed decisions at stage boundaries. This satisfies the PRINCE2 principle of defined roles and responsibilities, ensuring the board maintains oversight without requiring detailed Checkpoint Reports, which are reserved for the Team Manager.

  • ✗

    Senior Supplier

    Why it's wrong here

    Highlight Reports go to the Project Board, not the Senior Supplier, who is a Project Board member receiving them collectively. The Senior Supplier is tempting because they provide supplier resources and attend Project Board meetings, but reporting flows to the Board as a whole, not to that role individually.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative and specialist assistance to the Project Manager, such as maintaining the risk log and configuration management. Highlight Reports are produced by the Project Manager and sent to the Project Board, not to Project Support.

  • ✗

    Team Manager

    Why it's wrong here

    Highlight Reports flow from the Project Manager to the Project Board, so a Team Manager is not a recipient. The Team Manager receives Checkpoint Reports from team members and escalates via the Project Manager. It would be tempting if the question concerned who supplies progress information upward within a work package, where the Team Manager is central.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.