- A
Prepare the Stage Plan for approval by the Project Board
The PM prepares Stage Plans.
- B
Provide independent assurance
Why wrong: Assurance is separate from the PM.
- C
Manage the project within tolerances
The PM manages within tolerances.
- D
Approve the Project Initiation Documentation
Why wrong: The Board approves PID.
- E
Chair the Project Board meetings
Why wrong: The Executive chairs the Board.
PRINCE2F People: organizations, teams, and leadership Practice Question
This PRINCE2F practice question tests your understanding of people: organizations, teams, and leadership. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO of the following are responsibilities of the Project Manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Prepare the Stage Plan for approval by the Project Board
Option A is correct because the Project Manager is responsible for preparing Stage Plans, which detail how a management stage will be executed, and submitting them to the Project Board for approval. This aligns with PRINCE2's principle of management by stages, where the Project Manager provides the detailed plan for the next stage.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Prepare the Stage Plan for approval by the Project Board
Why this is correct
The PM prepares Stage Plans.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Provide independent assurance
Why it's wrong here
Assurance is separate from the PM.
- ✓
Manage the project within tolerances
Why this is correct
The PM manages within tolerances.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Approve the Project Initiation Documentation
Why it's wrong here
The Board approves PID.
- ✗
Chair the Project Board meetings
Why it's wrong here
The Executive chairs the Board.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is confusing the Project Manager's role in preparing and presenting plans with the Project Board's role in approving them, and mistaking the Project Manager's participation in meetings for chairing them.
Detailed technical explanation
How to think about this question
In PRINCE2, the Project Manager operates within tolerances set by the Project Board for each management stage. If tolerances are forecast to be exceeded, the Project Manager must escalate an exception report to the Project Board, who then decides on corrective action. This ensures the Project Manager has delegated authority while maintaining board-level control over significant deviations.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People: organizations, teams, and leadership — study guide chapter
Learn the concepts, then practise the questions
- →
People: organizations, teams, and leadership practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
People: organizations, teams, and leadership — This question tests People: organizations, teams, and leadership — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Prepare the Stage Plan for approval by the Project Board — Option A is correct because the Project Manager is responsible for preparing Stage Plans, which detail how a management stage will be executed, and submitting them to the Project Board for approval. This aligns with PRINCE2's principle of management by stages, where the Project Manager provides the detailed plan for the next stage.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.