PRINCE2F PRINCE2 Processes Practice Question
Which process includes the activity of 'Authorize Work Packages'?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Controlling a Stage
Authorizing Work Packages is an activity in the Controlling a Stage process, where the Project Manager assigns work to Team Managers.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Directing a Project
Why it's wrong here
The Project Board does not authorize individual Work Packages.
- ✓
Controlling a Stage
Why this is correct
The Project Manager authorizes Work Packages as part of day-to-day management.
- ✗
Managing Product Delivery
Why it's wrong here
The Team Manager accepts Work Packages but does not authorize them.
- ✗
Starting Up a Project
Why it's wrong here
No work packages are authorized in this pre-project process.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.