Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which process includes the activity of 'Authorize Work Packages'?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Controlling a Stage

Authorizing Work Packages is an activity in the Controlling a Stage process, where the Project Manager assigns work to Team Managers.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Directing a Project

    Why it's wrong here

    The Project Board does not authorize individual Work Packages.

  • Controlling a Stage

    Why this is correct

    The Project Manager authorizes Work Packages as part of day-to-day management.

  • Managing Product Delivery

    Why it's wrong here

    The Team Manager accepts Work Packages but does not authorize them.

  • Starting Up a Project

    Why it's wrong here

    No work packages are authorized in this pre-project process.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.