PRINCE2F PRINCE2 Processes Practice Question
A project is in the Managing a Stage Boundary process. The Project Manager has produced an End Stage Report. What else must be produced?
⚠ Common exam trap
Watch out — candidates often confuse the End Stage Report with the only output of the Managing a Stage Boundary process, forgetting that the next Stage Plan is a mandatory parallel output to enable stage authorization.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Stage Plan for the next stage
In the Managing a Stage Boundary process, the Project Manager produces an End Stage Report to summarize the current stage's performance. The PRINCE2 method requires that a Stage Plan for the next stage must also be produced during this process, as it provides the detailed plan for the upcoming work and is essential for the Project Board to authorize the next stage. Without the next Stage Plan, the project cannot proceed beyond the current stage boundary.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.