Courseiva
PRINCE2 PracticesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which TWO of the following are typical responsibilities of the Project Board?

⚠ Common exam trap

PRINCE2 often tests the distinction between 'defining' and 'approving' acceptance criteria, and between 'providing assurance' and 'being the board' — candidates mistakenly assign definition and assurance tasks to the Project Board when they actually belong to the Senior User and Project Assurance, respectively.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Authorizing the start of each stage

The Project Board is responsible for authorizing the start of each stage, including the initiation stage, by approving the Stage Plan and committing the required resources. This ensures that management stage boundaries are formally controlled and that the project remains aligned with the business case. Option D is correct because the Project Board approves the Project Plan (the overall plan for the project) to confirm that it is viable and consistent with the business case before the project proceeds.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Authorizing the start of each stage

    Why this is correct

    The Project Board authorizes stage starts based on stage plans.

  • Defining the project's acceptance criteria

    Why it's wrong here

    Acceptance criteria are defined by the Senior User, a Board member, but not the Board collectively.

  • Providing day-to-day management of the project

    Why it's wrong here

    Day-to-day management is the Project Manager's responsibility.

  • Approving the Project Plan

    Why this is correct

    The Project Board approves the Project Plan.

  • Providing independent assurance

    Why it's wrong here

    Assurance is delegated by the Board but may be performed by others; it is not typically a direct Board responsibility.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.