PRINCE2F PRINCE2 Processes Practice Question
During the Managing Product Delivery process, who produces the Checkpoint Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Team Manager
The Team Manager is responsible for producing Checkpoint Reports to inform the Project Manager of progress within a Work Package.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Manager
Why it's wrong here
The Project Manager receives Checkpoint Reports and reviews progress, but does not write them. Within Managing Product Delivery, the Team Manager produces the Checkpoint Report for the Project Manager. Selecting the Project Manager is tempting given overall accountability, yet the work package level owns this report.
- ✓
Team Manager
Why this is correct
The Team Manager produces Checkpoint Reports to update the Project Manager on work package progress, remaining effort and issues. This satisfies Managing Product Delivery, where the Team Manager controls work package delivery and reports at agreed frequency.
- ✗
Project Support
Why it's wrong here
Project Support administers tools and configuration management, not progress reporting. The Team Manager authors Checkpoint Reports during Managing Product Delivery. Choosing Project Support is tempting because it handles documentation, but it lacks the work-package delivery responsibility that generates the report's content.
- ✗
Project Board
Why it's wrong here
The Project Board receives Checkpoint Reports and escalates, but does not author them. The Team Manager produces Checkpoint Reports during Managing Product Delivery. Choosing the Board is tempting because it owns tolerance decisions, yet authorship sits with the team delivering the work package.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.