Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

According to PRINCE2, when should the Project Board meet?

⚠ Common exam trap

PeopleCert often tests the misconception that the Project Board meets on a fixed schedule (e.g., monthly or weekly), but PRINCE2 explicitly ties board meetings to stage boundaries and exception events, not arbitrary time intervals.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

At each stage boundary and when an Exception Report is raised

In PRINCE2, the Project Board is the decision-making body that provides overall direction and control. The board meets at each stage boundary to review progress, approve the next stage plan, and assess continued business justification. It also meets when an Exception Report is raised, which signals that a stage is forecast to exceed its tolerances, requiring the board to decide on corrective action.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Only at the start and end of the project

    Why it's wrong here

    They meet at each stage boundary.

  • At each stage boundary and when an Exception Report is raised

    Why this is correct

    This is the correct answer.

  • Monthly

    Why it's wrong here

    There is no fixed frequency.

  • Weekly

    Why it's wrong here

    The PM reports via Highlight Reports; the Board does not meet weekly.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. The Project Board is meeting to authorize the start of a new stage. According to PRINCE2, how frequently should the Project Board meet?

medium
  • A.At stage boundaries and when an exception is raised
  • B.Weekly
  • C.At the start and end of the project only
  • D.Monthly

Why A: The Project Board meets at key decision points in the project, specifically at stage boundaries and when an exception is raised. This aligns with PRINCE2's management-by-stage approach, where the Board authorizes each stage and handles exceptions. Option A correctly states this, while options B, C, and D do not reflect PRINCE2's recommended frequency.

Variation 2. The Project Board has not met for several months. According to PRINCE2, when should the Project Board meet?

medium
  • A.Weekly
  • B.Monthly
  • C.At stage boundaries and when an Exception Report is raised
  • D.Only at the end of the project

Why C: PRINCE2 recommends that Project Boards meet at the end of each management stage (Stage Boundary) and when an Exception Report is raised. They should not meet on a fixed monthly basis; meetings are exception-driven.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.