PRINCE2F PRINCE2 Practices Practice Question
Which risk response is appropriate for a threat that the project team decides to proactively manage by reducing the probability or impact?
⚠ Common exam trap
In PRINCE2, the Reduce response is proactive but does not eliminate the risk, whereas Avoid eliminates the threat entirely. Candidates often confuse 'proactive management' with 'avoidance,' but Avoid means changing the plan to remove the risk source, not just reducing it.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Reduce
Reduce is the correct risk response because it involves implementing actions to lower the probability or impact of a threat while still accepting that the risk may occur. In PRINCE2, this is a proactive response where the project team actively manages the risk by, for example, adding redundancy or conducting more frequent testing to decrease the likelihood of failure. The key is that the risk is not eliminated entirely but its effects are mitigated.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Reduce
Why this is correct
Reduce means taking action to lower probability or impact.
- ✗
Avoid
Why it's wrong here
Avoid means changing the plan to eliminate the threat.
- ✗
Transfer
Why it's wrong here
Transfer means shifting the risk to a third party.
- ✗
Accept
Why it's wrong here
Accept means acknowledging the risk without proactive action.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which risk response is appropriate for a threat that the project team decides to actively reduce the probability or impact of?
medium- A.Avoid
- B.Accept
- ✓ C.Reduce
- D.Transfer
Why C: The 'Reduce' response involves proactive actions to lower the probability and/or impact of a threat.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.