Which risk response is appropriate for a threat that the project team decides to proactively manage by reducing the probability or impact?

⚠ Common exam trap

In PRINCE2, the Reduce response is proactive but does not eliminate the risk, whereas Avoid eliminates the threat entirely. Candidates often confuse 'proactive management' with 'avoidance,' but Avoid means changing the plan to remove the risk source, not just reducing it.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Reduce

Reduce is the correct risk response because it involves implementing actions to lower the probability or impact of a threat while still accepting that the risk may occur. In PRINCE2, this is a proactive response where the project team actively manages the risk by, for example, adding redundancy or conducting more frequent testing to decrease the likelihood of failure. The key is that the risk is not eliminated entirely but its effects are mitigated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Reduce

    Why this is correct

    Reduce means taking action to lower probability or impact.

  • ✗

    Avoid

    Why it's wrong here

    Avoid eliminates the threat entirely by removing its cause or changing scope, so probability and impact are not reduced but designed out. It is tempting because it sounds proactive, yet it applies when the project can restructure to sidestep the risk completely, not mitigate it.

  • ✗

    Transfer

    Why it's wrong here

    Transfer shifts financial ownership of the threat to a third party such as an insurer or supplier, leaving probability and impact unchanged for the project itself. It suits risks whose consequences can be contractually borne elsewhere, not those the team actively reduces through mitigation work.

  • ✗

    Accept

    Why it's wrong here

    Accept acknowledges the threat and establishes contingency plans without altering its probability or impact, so no proactive reduction occurs. It fits low-priority threats where the cost of mitigation outweighs the exposure, not threats the team has decided to actively manage down.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which risk response is appropriate for a threat that the project team decides to actively reduce the probability or impact of?

medium
  • A.Avoid
  • B.Accept
  • ✓ C.Reduce
  • D.Transfer

Why C: In PRINCE2, 'Reduce' is the risk response that involves taking action to reduce the probability and/or impact of a threat. This is also known as mitigation. The question explicitly states the team decides to actively reduce probability or impact, which maps directly to the Reduce response.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.