- A
Raise an Exception Report to the Project Board
This is the correct escalation route when stage tolerances are forecast to be exceeded.
- B
Increase the stage budget within project tolerance
Why wrong: The Project Manager cannot unilaterally increase the budget; changes to tolerances require Project Board approval.
- C
Continue and report in the next Highlight Report
Why wrong: Continuing without immediate escalation violates the exception principle.
- D
Close the project as the Business Case is no longer viable
Why wrong: The SRO decides on Business Case viability; a stage tolerance breach does not automatically close the project.
PRINCE2F People: organizations, teams, and leadership Practice Question
This PRINCE2F practice question tests your understanding of people: organizations, teams, and leadership. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Raise an Exception Report to the Project Board
In PRINCE2, when a project manager forecasts that a stage will exceed its stage tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager has authority only within the agreed stage tolerance; exceeding it requires the Project Board to decide on corrective action, such as approving a revised plan or closing the project.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Raise an Exception Report to the Project Board
Why this is correct
This is the correct escalation route when stage tolerances are forecast to be exceeded.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Increase the stage budget within project tolerance
Why it's wrong here
The Project Manager cannot unilaterally increase the budget; changes to tolerances require Project Board approval.
- ✗
Continue and report in the next Highlight Report
Why it's wrong here
Continuing without immediate escalation violates the exception principle.
- ✗
Close the project as the Business Case is no longer viable
Why it's wrong here
The SRO decides on Business Case viability; a stage tolerance breach does not automatically close the project.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PeopleCert often tests the misconception that the Project Manager can adjust budgets within project tolerance even when stage tolerance is breached, but the correct action is always to escalate via an Exception Report when stage tolerance is forecast to be exceeded.
Detailed technical explanation
How to think about this question
Under PRINCE2, stage tolerance is a delegated authority limit set by the Project Board in the Stage Plan. The Project Manager must monitor actual costs against the stage budget and forecast; if the forecast exceeds tolerance, an Exception Report is mandatory, detailing the deviation, options, and recommendations. The Project Board then decides whether to approve a revised plan (e.g., by increasing tolerance or changing scope) or terminate the project, ensuring the Business Case remains viable.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People: organizations, teams, and leadership — study guide chapter
Learn the concepts, then practise the questions
- →
People: organizations, teams, and leadership practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
People: organizations, teams, and leadership — This question tests People: organizations, teams, and leadership — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Raise an Exception Report to the Project Board — In PRINCE2, when a project manager forecasts that a stage will exceed its stage tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager has authority only within the agreed stage tolerance; exceeding it requires the Project Board to decide on corrective action, such as approving a revised plan or closing the project.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.