Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

⚠ Common exam trap

PeopleCert often tests the misconception that the Project Manager can adjust budgets within project tolerance even when stage tolerance is breached, but the correct action is always to escalate via an Exception Report when stage tolerance is forecast to be exceeded.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

In PRINCE2, when a project manager forecasts that a stage will exceed its stage tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager has authority only within the agreed stage tolerance; exceeding it requires the Project Board to decide on corrective action, such as approving a revised plan or closing the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Raise an Exception Report to the Project Board

    Why this is correct

    This is the correct escalation route when stage tolerances are forecast to be exceeded.

  • Increase the stage budget within project tolerance

    Why it's wrong here

    The Project Manager cannot unilaterally increase the budget; changes to tolerances require Project Board approval.

  • Continue and report in the next Highlight Report

    Why it's wrong here

    Continuing without immediate escalation violates the exception principle.

  • Close the project as the Business Case is no longer viable

    Why it's wrong here

    The SRO decides on Business Case viability; a stage tolerance breach does not automatically close the project.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.