Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

In which process does the Project Board authorize the next stage of a project?

⚠ Common exam trap

The trap is that candidates may think Managing a Stage Boundary authorizes the next stage because it prepares the plan, but the actual authorization decision is made by the Project Board in Directing a Project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Directing a Project

The Project Board authorizes the next stage of a project during the Directing a Project process. In this process, the Project Board makes key decisions, including stage authorization, based on the Stage Plan prepared in the Managing a Stage Boundary process. Therefore, authorization is a direct responsibility of the Directing a Project process, not Managing a Stage Boundary.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Directing a Project

    Why this is correct

    Directing a Project is the process where the Project Board retains accountability, authorising each stage boundary via the 'authorise a stage or exception plan' activity. It satisfies the stem's requirement for the Board's stage authorisation, distinct from Managing a Stage Boundary, which merely prepares the next Stage Plan for approval.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary is where the Project Manager prepares the End Stage Report and next Stage Plan, then requests authorisation. The Board's decision to authorise the next stage occurs in the Directing a Project process, not within Managing a Stage Boundary itself.

  • ✗

    Initiating a Project

    Why it's wrong here

    Initiating a Project produces the Project Initiation Documentation and business case for board approval; it does not authorise subsequent stages. The Board authorises each next stage at a stage boundary, after reviewing the End Stage Report and next Stage Plan.

  • ✗

    Controlling a Stage

    Why it's wrong here

    Controlling a Stage is where the Project Manager manages day-to-day work, not where the Project Board authorises the next stage. It is tempting because stage boundaries and tolerances are monitored here, but the Board's authorisation decision happens in Managing a Stage Boundary, which seeks approval to proceed.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.