Courseiva
PRINCE2 Practices →easyMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

In PRINCE2, who is responsible for the Business Case?

⚠ Common exam trap

Many candidates confuse the Project Manager's role in maintaining the Business Case with ownership, but PRINCE2 explicitly assigns accountability to the Executive, not the manager who writes or updates it.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Executive

The Executive is the single individual responsible for the Business Case in PRINCE2. They own the project's justification and ensure it remains viable throughout the project lifecycle, approving any changes that affect its viability. The Business Case is the Executive's primary accountability, as defined in the PRINCE2 manual.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those delivering the products and provides supplier resources; accountability for the Business Case rests with the Executive, who owns the business justification. A supplier is tempted to claim this because they build the solution, but their interest is delivery capability, not ongoing business value.

  • ✗

    The Project Manager

    Why it's wrong here

    The Project Manager prepares and maintains the Business Case on the Executive's behalf, but accountability stays with the Executive, who owns the justification. Delegation is tempting because the Project Manager does the drafting, yet responsibility for continued business justification cannot be transferred.

  • ✗

    The Senior User

    Why it's wrong here

    The Senior User specifies requirements and represents those using the product, providing user resources and benefits realisation input. They are tempted because benefits accrue to users, but accountability for the Business Case belongs to the Executive, who owns the business justification across all stakeholder interests.

  • ✓

    The Executive

    Why this is correct

    The Executive owns the Business Case in PRINCE2, as defined by the management-by-stage principle and the business justification theme. This satisfies the constraint that the Business Case must have a single, accountable owner who is ultimately responsible for ensuring the project remains viable and aligned with corporate objectives.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.