In PRINCE2, which process is triggered by a request from the Project Manager to the Team Manager to deliver a product?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Managing Product Delivery

The Managing Product Delivery process covers the acceptance and delivery of work packages. Option B is correct. CS includes the request but MP is the Team Manager's process. DP is for the Project Board. SU is for starting up.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Starting Up a Project

    Why it's wrong here

    SU is a pre-project process.

  • Managing Product Delivery

    Why this is correct

    MP is the process for Team Managers to deliver work packages.

  • Directing a Project

    Why it's wrong here

    DP is the Project Board process.

  • Controlling a Stage

    Why it's wrong here

    CS is the Project Manager's process; the work package is authorized in CS but delivery is in MP.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.