Courseiva
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

What is the difference between a Request for Change (RFC) and an Off-specification?

⚠ Common exam trap

PeopleCert often tests the confusion between 'change to a baseline' (RFC) and 'failure to meet a requirement' (Off-specification), trapping candidates who focus on who raises or approves the issue rather than the fundamental nature of the problem.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

An RFC is a change to an approved baseline, while an Off-specification is a deviation from a requirement.

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify an approved baseline (e.g., a product description, plan, or schedule), whereas an Off-specification is a formal notification that a product or component does not meet its specified requirements or quality criteria. The core distinction lies in the nature of the issue: an RFC seeks to change what was agreed, while an Off-specification reports a failure to deliver what was agreed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • An RFC is raised by the Project Board, while an Off-specification is raised by the Project Manager.

    Why it's wrong here

    Both can be raised by anyone; the issuer is not the distinguishing factor.

  • An RFC is always approved by the Change Authority, while an Off-specification is approved by the Project Board.

    Why it's wrong here

    The approval level depends on delegated authority, not the issue type.

  • An RFC is a change to an approved baseline, while an Off-specification is a deviation from a requirement.

    Why this is correct

    An RFC proposes a change to an approved baseline; an Off-specification is a failure to meet a specified requirement.

  • An Off-specification can be resolved by concession, while an RFC cannot.

    Why it's wrong here

    A concession can be used for an Off-specification, but an RFC may also be rejected or deferred.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.