PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A project is nearing the end of its final stage. The Project Manager has prepared the End Project Report and a Lessons Report. Which process is responsible for authorising the project closure?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

Directing a Project (DP) is the process by which the Project Board authorises project closure. The Project Manager prepares the closure recommendation in Closing a Project, but the Board gives the final authorisation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Closing a Project

    Why it's wrong here

    Closing a Project prepares the closure recommendation and reports, but the Project Board authorises closure through DP.

  • Managing a Stage Boundary

    Why it's wrong here

    SB is for stage transitions, not final closure.

  • Directing a Project

    Why this is correct

    DP is the process where the Project Board makes key decisions, including authorising closure.

  • Controlling a Stage

    Why it's wrong here

    Controlling a Stage manages the work of a stage and reports progress, but it does not include the authority to close the project; that authority resides in the Directing a Project process, which reviews the End Project Report and Lessons Report to give formal closure approval. It is tempting because Controlling a Stage handles stage-level authorisations and corrective actions, so in a scenario where a premature stage-end required approval to proceed, that process would be correct.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project is in its final stage. The Project Manager has prepared the End Project Report and Lessons Report. What must happen before the project can be closed?

hard
  • A.The final products must be delivered to the operations team
  • B.The Business Case must be updated with actual costs and benefits
  • C.The Project Board must approve the End Project Report and authorize closure
  • D.The project team must be released

Why C: The Project Board must authorize project closure through the Directing a Project process. The PM prepares the recommendation, but only the Board can formally close.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.