Which TWO of the following are outputs of the Starting Up a Project process?
⚠ Common exam trap
Watch out — candidates often confuse the Project Brief (output of Starting Up a Project) with the Project Initiation Documentation (PID) (output of Initiating a Project), or mistakenly think the Benefits Management Approach is created early, when it is actually developed during initiation.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Initiation Stage Plan
The Starting Up a Project process is the pre-project phase where the project board is appointed, the project brief is created, and the initiation stage plan is produced. The Initiation Stage Plan (A) is a direct output because it details the activities, resources, and controls needed for the initiation stage itself, enabling the project board to authorize the next process. The Project Brief (B) is also an output as it captures the initial business justification, scope, and approach, forming the basis for the project mandate and subsequent detailed planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Initiation Stage Plan
Why this is correct
Correct. The plan for the initiation stage is produced in SU.
- ✓
Project Brief
Why this is correct
The Project Brief is an output of Starting Up a Project because it consolidates the project mandate, outline business case, and project approach into a single document that authorises the initiation stage. This satisfies the constraint that the process must produce sufficient information for the Project Board to decide whether to proceed to initiation.
- ✗
Benefits Management Approach
Why it's wrong here
Benefits Management Approach is produced in IP.
- ✗
Project Initiation Documentation (PID)
Why it's wrong here
PID is output of IP, not SU.
- ✗
End Stage Report
Why it's wrong here
End Stage Report is output of SB.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.