Courseiva
PRINCE2 ProcesseseasyMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which TWO of the following are outputs of the Starting Up a Project process?

⚠ Common exam trap

Watch out — candidates often confuse the Project Brief (output of Starting Up a Project) with the Project Initiation Documentation (PID) (output of Initiating a Project), or mistakenly think the Benefits Management Approach is created early, when it is actually developed during initiation.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiation Stage Plan

The Starting Up a Project process is the pre-project phase where the project board is appointed, the project brief is created, and the initiation stage plan is produced. The Initiation Stage Plan (A) is a direct output because it details the activities, resources, and controls needed for the initiation stage itself, enabling the project board to authorize the next process. The Project Brief (B) is also an output as it captures the initial business justification, scope, and approach, forming the basis for the project mandate and subsequent detailed planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiation Stage Plan

    Why this is correct

    Correct. The plan for the initiation stage is produced in SU.

  • Project Brief

    Why this is correct

    The Project Brief is an output of Starting Up a Project because it consolidates the project mandate, outline business case, and project approach into a single document that authorises the initiation stage. This satisfies the constraint that the process must produce sufficient information for the Project Board to decide whether to proceed to initiation.

  • Benefits Management Approach

    Why it's wrong here

    Benefits Management Approach is produced in IP.

  • Project Initiation Documentation (PID)

    Why it's wrong here

    PID is output of IP, not SU.

  • End Stage Report

    Why it's wrong here

    End Stage Report is output of SB.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.