Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

Who is responsible for producing the Checkpoint Report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Team Manager

The Team Manager produces the Checkpoint Report for the Project Manager to report progress of a Work Package.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative assistance such as maintaining the risk log and configuration records, not authoring Checkpoint Reports. It tempts because support staff handle documentation and information management, so report production appears administrative, yet PRINCE2 assigns this to the Team Manager.

  • ✓

    Team Manager

    Why this is correct

    The Team Manager produces Checkpoint Reports at each checkpoint, reporting progress, issues and forecast to the Project Manager. This satisfies the stem's requirement because checkpoint reporting sits within the Managing a Stage Boundary-adjacent team-level monitoring duty, not the Project Manager's or Project Board's remit.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager receives Checkpoint Reports from team managers and reviews progress, but does not author them; that is the Team Manager's task. It tempts because the Project Manager owns the Highlight Report and overall delivery accountability, so the reporting duty appears to sit with them.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests on the Project Board and specifies requirements; Checkpoint Reports are produced by Team Managers during stage execution. It tempts because Senior Users receive progress information, but their role is board-level direction, not routine team-level reporting.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.