During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction before proceeding

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally decide to exceed tolerances; that requires Project Board authorisation. Option A is wrong because the PM cannot increase the budget without Project Board approval. Option B is wrong because closing the project is not the appropriate response to a stage tolerance breach; the Project Board may decide to close if the Business Case is no longer viable. Option C is wrong because continuing without escalation violates management by exception.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Increase the project budget to absorb the additional cost and continue with the current Stage Plan

    Why it's wrong here

    The Project Manager cannot unilaterally increase the project budget. Changes to project-level tolerances require Project Board authorisation.

  • Close the project immediately as the Business Case is no longer viable

    Why it's wrong here

    A cost tolerance breach does not automatically mean the Business Case is unviable. The Project Board must assess the situation and decide whether to continue, change direction, or close.

  • Continue with the current Stage Plan and report the cost overrun in the next Highlight Report

    Why it's wrong here

    Continuing without escalation when a tolerance is forecast to be exceeded violates PRINCE2's management by exception principle.

  • Raise an Exception Report to the Project Board and await their direction before proceeding

    Why this is correct

    When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.