Question 890 of 1,731
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

This PRINCE2F practice question tests your understanding of people: organizations, teams, and leadership. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

In PRINCE2, when a project manager forecasts that a stage will exceed its cost tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated limits, and exceeding them requires board-level decision-making, not just reporting or self-authorization. The Exception Report triggers an Exception Plan to recover or adjust the project.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Report the overrun in the next Highlight Report

    Why it's wrong here

    Highlight Reports are routine; an Exception Report is needed for immediate escalation.

  • Raise an Exception Report to the Project Board

    Why this is correct

    Correct action: escalate immediately via Exception Report.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Close the project as the Business Case is no longer viable

    Why it's wrong here

    Only the Project Board can decide to close the project based on the Exception Report.

  • Increase the stage budget and continue

    Why it's wrong here

    The Project Manager cannot change tolerances; only the Project Board can authorize changes.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PeopleCert often tests the distinction between reporting (Highlight Report) and escalation (Exception Report), trapping candidates who think a simple status update suffices when tolerances are breached.

Detailed technical explanation

How to think about this question

Under PRINCE2, cost tolerance is a delegated authority from the Project Board to the Project Manager for a specific stage. If the forecast exceeds this tolerance, the Project Manager must raise an Exception Report, which includes the cause, impact, options, and a recommended Exception Plan. The Project Board then decides whether to approve the Exception Plan, which may involve adjusting tolerances, changing scope, or even premature closure. This mechanism ensures control remains with the board and prevents unauthorized budget overruns.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A junior network technician can log in to a core router but cannot reach the enable prompt or configuration mode. The AAA server is authenticating the login — but the authorisation policy only grants privilege level 1, not 15. Authentication (who you are) is working; authorisation (what you can do) is not.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

People: organizations, teams, and leadership — This question tests People: organizations, teams, and leadership — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Raise an Exception Report to the Project Board — In PRINCE2, when a project manager forecasts that a stage will exceed its cost tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated limits, and exceeding them requires board-level decision-making, not just reporting or self-authorization. The Exception Report triggers an Exception Plan to recover or adjust the project.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.