PRINCE2F People: organizations, teams, and leadership Practice Question
Which of the following is NOT a responsibility of the Project Manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Performing Project Assurance
Project Assurance is independent and cannot be delegated to the Project Manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Preparing Highlight Reports for the Project Board
Why it's wrong here
This is a PM responsibility.
- ✓
Performing Project Assurance
Why this is correct
Project Assurance is independent and cannot be performed by the PM.
- ✗
Authorizing work packages for the Team Manager
Why it's wrong here
The PM authorizes work packages.
- ✗
Managing the project within tolerances
Why it's wrong here
This is a core PM responsibility.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.