In the Progress practice, who receives the Highlight Report?

⚠ Common exam trap

A common pitfall in PRINCE2 exams is confusing who produces the Highlight Report (Project Manager) with who receives it (Project Board). Also, candidates may incorrectly think that individual Project Board members like the Senior User receive the report separately, but it is sent to the entire Project Board.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

The Highlight Report is a progress report that provides the Project Board with a summary of the project's status at a frequency defined in the Communication Management Approach. It is specifically designed to keep the Project Board informed of progress, achievements, and any issues or risks that require their attention. The Project Board is the sole recipient of the Highlight Report, as they are responsible for overall project governance and decision-making.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Support

    Why it's wrong here

    Project Support is an administrative role that maintains tooling, configuration management and document repositories; it does not receive the Highlight Report as a governance communication. It would be involved where project office duties such as maintaining the project's information baseline are required, not progress reporting to management.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests on the Project Board and receives reports such as the End Stage Report at decision points, not the periodic Highlight Report. It would be the right recipient where user acceptance, benefits realisation or stage boundary approval decisions are being sought from the board.

  • ✓

    Project Board

    Why this is correct

    The Highlight Report is a progress report sent by the Project Manager to the Project Board at agreed intervals, summarising stage status. This satisfies the stem by identifying the Project Board as the recipient within the Progress practice.

  • ✗

    Team Manager

    Why it's wrong here

    The Team Manager receives Work Packages and supplies Checkpoint Reports upward to the Project Manager; the Highlight Report flows the other way, to the Project Board. It would be correct where the question asked who provides regular progress information to the Project Manager during a stage.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.