Courseiva
People: organizations, teams, and leadershipeasyMultiple ChoiceObjective-mapped

Who Is Responsible for Maintaining the Business Case in PRINCE2?

In PRINCE2, who is responsible for maintaining the Business Case throughout the project?

Quick Answer

The answer is the Senior Responsible Owner, also known as the Executive in PRINCE2. This role is accountable for maintaining the Business Case throughout the project because the Business Case is the central document that justifies the project’s initiation and ongoing viability; only the Executive has the authority to approve changes to it or decide to close the project if it is no longer justified. On the PRINCE2 Foundation exam, this question tests your understanding of the project board’s responsibilities, specifically that the Executive owns the Business Case while the Senior User defines the benefits and the Senior Supplier provides resources. A common trap is confusing the Executive with the Project Manager, who only compiles and updates the Business Case but does not maintain it. Remember the mnemonic: “Executive owns the case, Project Manager keeps the pace.”

⚠ Common exam trap

The trap is confusing accountability with responsibility. The Executive (Senior Responsible Owner) is accountable for the Business Case and decides whether to continue the project based on its viability, but the Project Manager is responsible for the actual maintenance and updates throughout the project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

In PRINCE2, the Project Manager is responsible for maintaining the Business Case on a day-to-day basis. This includes monitoring actual benefits against the expected benefits, updating the Business Case with any changes, and reporting to the Project Board. The Executive is accountable for the Business Case and makes decisions based on its viability, but the Project Manager handles the maintenance activities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Responsible Owner (Executive)

    Why it's wrong here

    Incorrect. The Executive is accountable for the Business Case, not responsible for its maintenance. They approve changes and decide on continuation, but the Project Manager does the maintenance.

  • Project Manager

    Why this is correct

    The Project Manager is responsible for maintaining the Business Case because PRINCE2 mandates that the Project Manager continuously updates the Business Case to reflect approved changes, risks, and progress, satisfying the constraint that the Business Case must remain viable throughout the project’s lifecycle. This duty is distinct from the Senior User, who provides the benefits, and the Executive, who owns the Business Case.

  • Senior Supplier

    Why it's wrong here

    Incorrect. The Senior Supplier provides supplier resources and expertise but has no direct responsibility for maintaining the Business Case.

  • Project Assurance

    Why it's wrong here

    Incorrect. Project Assurance provides independent oversight and checks that the project is being run correctly but does not maintain the Business Case.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

5 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In PRINCE2, which role is responsible for ensuring that the business case is maintained and that the project remains viable?

easy
  • A.Senior Responsible Owner (Executive)
  • B.Senior Supplier
  • C.Senior User
  • D.Project Manager

Why A: The Senior Responsible Owner (Executive) is the single person accountable for the business case and for ensuring that the project remains viable throughout its lifecycle. They own the business justification and have the authority to stop the project if it no longer meets the organization's objectives or if the costs outweigh the benefits.

Variation 2. Which role is responsible for maintaining the Business Case throughout the project?

easy
  • A.Senior User
  • B.Project Manager
  • C.Senior Responsible Owner (Executive)
  • D.Project Support

Why C: In PRINCE2, the Senior Responsible Owner (Executive) is the role ultimately accountable for the Business Case and its maintenance throughout the project. This includes ensuring the Business Case remains viable and aligned with organizational objectives, and that any necessary updates are made as the project progresses. The Executive owns the Business Case from the initial idea through to project closure.

Variation 3. Which role is responsible for maintaining the Business Case throughout the project?

easy
  • A.Project Manager
  • B.Senior User
  • C.Executive (Senior Responsible Owner)
  • D.Project Assurance

Why C: The Executive (Senior Responsible Owner) is accountable for the Business Case and its maintenance throughout the project. The Project Manager develops and maintains the Business Case on behalf of the Executive, but accountability rests with the Executive.

Variation 4. Which role is responsible for maintaining the Business Case throughout the project?

easy
  • A.Senior Responsible Owner (Executive)
  • B.Project Assurance
  • C.Project Manager
  • D.Senior User

Why A: The Senior Responsible Owner (SRO/Executive) owns the Business Case and is accountable for ensuring it remains viable. The Project Manager maintains the Business Case on behalf of the Executive.

Variation 5. Which role is responsible for maintaining the Business Case throughout the project?

easy
  • A.Senior Supplier
  • B.Project Manager
  • C.Senior User
  • D.Executive (Senior Responsible Owner)

Why D: The Executive (Senior Responsible Owner) is accountable for the Business Case and ensuring it remains viable. The Project Manager maintains it on a day-to-day basis, but the Executive holds ultimate responsibility.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.