PRINCE2F People: organizations, teams, and leadership Practice Question

A stakeholder is concerned that the project is not delivering value for money. Which role should this concern be raised with?

⚠ Common exam trap

It's easy for candidates to confuse the Project Manager's responsibility for day-to-day cost control with the Executive's accountability for overall value for money and the Business Case.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

The Executive is ultimately accountable for the project's business justification, including ensuring value for money. Concerns about cost versus benefits must be escalated to the Executive, who owns the Business Case and has the authority to approve changes or stop the project if value is not being delivered.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User specifies requirements and monitors that the solution delivers expected benefits to users, but accountability for the business case and value for money sits with the Business Sponsor. The Senior User would be correct for concerns about solution fitness or user benefit delivery.

  • ✗

    Project Assurance

    Why it's wrong here

    Project Assurance independently monitors the project on behalf of the Board against business, user and supplier interests, but it does not own the business case. Value-for-money accountability rests with the Business Sponsor. Project Assurance would be correct for verifying that defined governance and controls are being followed.

  • ✓

    Executive

    Why this is correct

    The Executive is accountable for the business case and therefore owns value-for-money assurance. Concerns about whether the project justifies its investment are escalated to this role, which sits on the Project Board and represents business interests.

  • ✗

    Project Manager

    Why it's wrong here

    Value for money is a business case concern owned by the Business Sponsor, who is accountable for benefits realisation and continued viability. The Project Manager handles day-to-day delivery within tolerances, not investment justification. Raising it here misdirects a strategic concern to an operational role.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.