In the Organising practice, what is the single point of accountability for the project's business justification?

⚠ Common exam trap

Watch out — candidates often confuse the Project Board's collective responsibility with the Executive's singular accountability, or mistakenly assign business justification to the Project Manager who manages the business case but does not own it.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Executive (Senior Responsible Owner)

In PRINCE2, the Executive (Senior Responsible Owner) is the single point of accountability for the project's business justification. This role owns the business case, ensures the project remains viable, and has ultimate authority over its initiation, continuation, and closure. The Project Manager is accountable for day-to-day management, not the business justification.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Project Manager

    Why it's wrong here

    The Project Manager runs the project day to day on the board's delegated tolerance, but accountability for the business justification sits above that role. It is tempting because the Project Manager prepares the Business Case, and would be correct for the daily management of its production.

  • ✓

    The Executive (Senior Responsible Owner)

    Why this is correct

    The Executive is the single point of accountability for the project's business justification, owning the Business Case. This satisfies the Organising practice's requirement that one individual, not a committee, remains answerable for ensuring the project delivers value.

  • ✗

    The Senior User

    Why it's wrong here

    The Senior User represents user interests and benefits realisation, not the business justification itself. It is tempting because users do articulate benefits, and the role would be correct when specifying requirements and confirming the solution meets them.

  • ✗

    The Project Board

    Why it's wrong here

    The Project Board holds collective accountability, so it is not a single point; the Executive alone owns the business justification. It is tempting because the board does approve the Business Case, and would be correct when authorising the project and its continued viability.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.