What is the purpose of the Highlight Report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To provide the Project Board with a summary of stage progress

The Highlight Report is produced by the Project Manager and sent to the Project Board at regular intervals to provide a summary of progress during a stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To detail the work packages for the next stage

    Why it's wrong here

    This is part of the Stage Plan.

  • To provide the Project Board with a summary of stage progress

    Why this is correct

    This is the main purpose of the Highlight Report.

  • To report issues to the Project Board

    Why it's wrong here

    Issues are reported via issue reports, but the Highlight Report provides a broader summary.

  • To report team progress to the Project Manager

    Why it's wrong here

    That is the purpose of the Checkpoint Report.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.