Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A Project Manager is reviewing progress during a stage and discovers that a Work Package is behind schedule. The Team Manager has not submitted a Checkpoint Report this week. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Contact the Team Manager to understand the delay and agree corrective actions

The Project Manager should contact the Team Manager to understand the situation and take corrective action. This is part of the 'Review Work Package Status' activity in Controlling a Stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Close the Work Package and reassign the work to another team

    Why it's wrong here

    Closing a Work Package is a formal process; reassigning work may not address the root cause and could introduce risks.

  • Contact the Team Manager to understand the delay and agree corrective actions

    Why this is correct

    The PM should first assess the situation with the Team Manager and decide if corrective action within tolerance is possible.

  • Escalate the issue to the Project Board immediately via an Exception Report

    Why it's wrong here

    Only if the delay threatens stage tolerance should an Exception Report be raised. A minor delay may be handled within tolerance.

  • Update the Project Plan to reflect the delay and inform the Project Board in the next Highlight Report

    Why it's wrong here

    The PM should first address the issue before updating plans; the Highlight Report is for periodic reporting, not immediate escalation.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.