PRINCE2F People: organizations, teams, and leadership Practice Question
In PRINCE2, why is the Project Assurance role separated from the Project Manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To ensure that the Project Board has independent and objective advice.
Project Assurance provides independent oversight to ensure that the project is managed correctly. If the Project Manager also performed assurance, it would compromise objectivity and independence.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To reduce the workload of the Project Manager.
Why it's wrong here
Separation exists so the Project Board receives independent verification of the Project Manager's performance, not to lighten anyone's workload. It tempts because assurance does absorb monitoring tasks, but PRINCE2 frames the split around independence and the three stakeholder interests, not capacity relief.
- ✓
To ensure that the Project Board has independent and objective advice.
Why this is correct
Project Assurance provides the Project Board with independent, objective advice on whether the project remains viable, so separating it from the Project Manager prevents self-review of the manager's own performance and products. This satisfies the stem's constraint by preserving the board's independent oversight of the project.
- ✗
To align with the PRINCE2 principle of continued business justification.
Why it's wrong here
Continued business justification concerns the ongoing viability of the business case, which the Project Board owns; separation of Project Assurance exists to give the board independent verification of the Project Manager's work. It tempts because assurance does feed justification, but that principle is not the reason for the split.
- ✗
To allow the Project Manager to focus on delivery while Assurance handles quality.
Why it's wrong here
Project Assurance monitors all performance aspects — cost, timescale, quality, scope, risk and benefits — against the project's baselines, not quality alone. It tempts because quality review activity is visible assurance work, yet the role's independence from the Project Manager is the actual reason for separation.
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.