In PRINCE2, which role is responsible for providing an independent view of the project's progress and adherence to standards?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Assurance
Project Assurance provides an independent check on the project's progress and compliance, reporting to the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Support
Why it's wrong here
Project Support provides administrative and specialist assistance such as maintaining the project's files and tools, not independent assurance of progress and standards. It tempts because support staff often gather the data assurance reviews use, but Project Assurance is the role holding that independent monitoring mandate.
- ✓
Project Assurance
Why this is correct
Project Assurance provides the Project Board with an independent, objective view of the project's performance, products and adherence to standards, monitoring against the Business Case, plans and PRINCE2. Independence from the Project Manager is the defining characteristic that makes this monitoring credible.
- ✗
Project Manager
Why it's wrong here
The Project Manager runs the project day to day and reports progress, so cannot provide an independent view of it. It tempts because the role owns progress reporting and standards compliance operationally, but independence requires the separate Project Assurance role, which sits outside the management line.
- ✗
Senior User
Why it's wrong here
The Senior User represents user interests and specifies benefits and requirements, not independent assurance of progress and standards. It tempts because the Senior User sits on the Project Board and receives progress reports, but Project Assurance is the dedicated independent role checking adherence on the Board's behalf.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.