PRINCE2F PRINCE2 Practices Practice Question
Which PRINCE2 principle is being applied when a project uses management by exception?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Manage by exception
Management by exception is a key principle where tolerances are set and escalation occurs only when tolerances are forecast to be exceeded.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Continued business justification
Why it's wrong here
That principle relates to the Business Case.
- ✓
Manage by exception
Why this is correct
Correct principle.
- ✗
Manage by stages
Why it's wrong here
That principle is about planning and control by stages.
- ✗
Focus on products
Why it's wrong here
That principle relates to product-based planning.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.