Which PRINCE2 principle is being applied when a project uses management by exception?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Manage by exception

Management by exception is a key principle where tolerances are set and escalation occurs only when tolerances are forecast to be exceeded.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continued business justification

    Why it's wrong here

    That principle relates to the Business Case.

  • Manage by exception

    Why this is correct

    Correct principle.

  • Manage by stages

    Why it's wrong here

    That principle is about planning and control by stages.

  • Focus on products

    Why it's wrong here

    That principle relates to product-based planning.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.