PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are outputs of the Initiating a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Benefits Management Approach
The PID and the Benefits Management Approach are outputs of IP. The Project Brief is from SU, and the End Stage Report is from SB.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Benefits Management Approach
Why this is correct
Benefits Management Approach is created during IP.
- ✗
Project Brief
Why it's wrong here
Project Brief is output of SU.
- ✓
Project Initiation Documentation
Why this is correct
PID is the key output of IP.
- ✗
Exception Report
Why it's wrong here
Exception Report is produced when tolerances are exceeded.
- ✗
End Stage Report
Why it's wrong here
End Stage Report is output of Managing a Stage Boundary.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.