Courseiva
PRINCE2 ProcessesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which TWO of the following are outputs of the Initiating a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Benefits Management Approach

The PID and the Benefits Management Approach are outputs of IP. The Project Brief is from SU, and the End Stage Report is from SB.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Benefits Management Approach

    Why this is correct

    Benefits Management Approach is created during IP.

  • Project Brief

    Why it's wrong here

    Project Brief is output of SU.

  • Project Initiation Documentation

    Why this is correct

    PID is the key output of IP.

  • Exception Report

    Why it's wrong here

    Exception Report is produced when tolerances are exceeded.

  • End Stage Report

    Why it's wrong here

    End Stage Report is output of Managing a Stage Boundary.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.