Which process is triggered when the Project Manager identifies that a stage tolerance is forecast to be exceeded?
In Controlling a Stage, the Project Manager monitors progress and raises an Exception Report when tolerances are forecast to be exceeded.
Why this answer
The Exception Plan is produced during Managing a Stage Boundary, but the initial identification and escalation occur in Controlling a Stage, where the Exception Report is raised.