PRINCE2F PRINCE2 Processes Practice Question
Who is responsible for authorizing the initiation of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The Project Board is responsible for authorizing initiation during the Directing a Project process. The Project Manager recommends, but the Board decides.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Manager
Why it's wrong here
The Project Manager recommends initiation but does not authorize it.
- ✗
Executive
Why it's wrong here
The Executive is part of the Project Board but the Board as a whole authorizes initiation.
- ✗
Senior User
Why it's wrong here
The Senior User is part of the Project Board but does not authorize alone.
- ✓
Project Board
Why this is correct
Correct. The Project Board authorizes initiation.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.