Who is responsible for maintaining the Business Case throughout the project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Executive

The Executive (Senior Responsible Owner) owns the Business Case and ensures its ongoing viability.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Team Manager

    Why it's wrong here

    Team Manager focuses on Work Packages.

  • Project Manager

    Why it's wrong here

    PM maintains the Business Case on behalf of the Executive, but ultimate ownership is with the Executive.

  • Executive

    Why this is correct

    The Executive is responsible for the Business Case.

  • Senior User

    Why it's wrong here

    Senior User specifies benefits but does not own the Business Case.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.