PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

What is the purpose of the Plans practice?

⚠ Common exam trap

Many exam-takers confuse the Plans practice with the Quality practice, mistakenly thinking that plans define quality criteria, when in fact plans focus on the sequence and means of product delivery, not the quality standards.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

To facilitate communication and control by defining the means of delivering the products

The Plans practice defines the means of delivering the products by establishing a structured approach to planning, including the creation of project and stage plans. This facilitates communication and control by providing a clear roadmap for stakeholders and enabling progress tracking against baselines. It is not about defining quality criteria, managing changes, or assigning roles, which are covered by other PRINCE2 practices.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    To define the project's quality criteria

    Why it's wrong here

    Quality criteria are defined and controlled through the Quality practice, not Plans, which addresses the levels, content and updating of plans. It is tempting because quality expectations appear within plan documentation, and this would be correct when the question concerns specifying measurable quality tolerances and acceptance criteria.

  • ✗

    To manage changes to project baselines

    Why it's wrong here

    Managing changes to baselines belongs to the Change practice, which handles issues and change control; Plans concerns producing and maintaining the project, stage and team plans. It is tempting because baselines are documented in plans, and this would be correct when the question asks which practice authorises and tracks changes to those baselines.

  • ✗

    To define the roles and responsibilities of the project team

    Why it's wrong here

    Plans practice produces and maintains the project's plans, defining products, schedules and costs across the delivery approaches. Team roles and responsibilities sit within the Organisation practice's role descriptions and project management team structure. It tempts because planning activities do allocate who produces each plan, but that is not the practice's purpose.

  • ✓

    To facilitate communication and control by defining the means of delivering the products

    Why this is correct

    The Plans practice produces and maintains the project, stage and team plans that define what products will be delivered, by whom, and when. This documented means of delivery underpins communication with stakeholders and provides the baseline for management control.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.