Which role is accountable for the project's success and chairs the Project Board?

⚠ Common exam trap

Test-takers frequently confuse accountability with responsibility, leading candidates to pick the Project Manager (who is responsible for delivery) instead of the Executive (who is accountable for success and chairs the Board).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

The Executive is the single individual accountable for the project's success and chairs the Project Board in PRINCE2. This role provides the business justification, secures funding, and makes key strategic decisions, ensuring the project remains viable and aligned with organizational objectives.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User specifies needs and benefits and represents users' interests on the Board. Accountability for the project's success and chairing the Board belongs to the Executive, who owns the business case and remains ultimately answerable.

  • ✓

    Executive

    Why this is correct

    The Executive is the single accountable owner of the project's business case and chairs the Project Board, holding overall accountability for success. This satisfies the stem's requirement for the role accountable and chairing the board.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager runs the project on the Board's behalf day to day, managing the team and producing the products. Accountability for success and chairing the Project Board sits with the Executive; the Project Manager reports to the Board rather than leading it.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those providing resources and expertise, and holds decision authority only over supplier-specific matters within the Project Board's supplier interest. Accountability for the project's success and chairing the Board rests with the Executive, who owns the business case.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.