PRINCE2 Practices →easyMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Which practice describes the project management team structure and defines roles and responsibilities?

⚠ Common exam trap

Watch out — candidates often confuse the Organising practice with the Plans practice, mistakenly thinking that defining the team structure is part of planning, when in PRINCE2 it is a separate practice focused specifically on roles and responsibilities.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Organising

The Organising practice defines the project management team structure, roles, and responsibilities, including the four levels of management (corporate/programme management, project board, project manager, and team manager) and the three project interests (business, user, supplier). It establishes clear accountability and authority within the PRINCE2 project management team.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Plans

    Why it's wrong here

    Plans describe products, activities, schedules and tolerances across the plan levels; they do not define who fills which role. It is tempting because a plan's product descriptions imply who delivers what, but the Organisation practice is what specifies the project management team structure and assigns roles and responsibilities.

  • ✗

    Business Case

    Why it's wrong here

    The Business Case justifies the project's continued viability by comparing benefits, costs and risks; it does not define team roles or reporting lines. It is tempting because the Business Case names the executive as accountable for benefits realisation, yet the Organisation practice is what actually documents the team structure and responsibilities.

  • ✓

    Organising

    Why this is correct

    Organising is the practice that defines the project management team structure, roles and responsibilities, and the layers of accountability within the project. It satisfies the stem's requirement by establishing who is accountable to whom, covering the project board, project manager, team manager and assurance roles.

  • ✗

    Progress

    Why it's wrong here

    Progress tracks achievement against the plan's baselines and forecasts, covering time and cost tolerances, not team structure. It is tempting because Progress does address accountability for delivering products, but role definitions and the project management team hierarchy belong to the Organisation practice, which assigns responsibilities.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.