A project is forecast to exceed its cost tolerance. What should the Project Manager do?

⚠ Common exam trap

Test-takers frequently confuse the Project Manager's authority to manage within tolerances with the ability to handle breaches, leading them to choose 'continue and report later' (D) or 'use change budget' (B), when PRINCE2 mandates immediate escalation via an Exception Report.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report and await Project Board direction.

C is correct because when a project forecasts exceeding its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is a PRINCE2 management by exception principle: tolerances are delegated limits, and exceeding them requires board-level decision-making, not unilateral action by the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Close the project as the Business Case is no longer viable.

    Why it's wrong here

    A cost overrun does not automatically mean the Business Case is unviable.

  • Increase the project budget using the change budget.

    Why it's wrong here

    The Project Manager cannot increase the budget without Project Board approval.

  • Raise an Exception Report and await Project Board direction.

    Why this is correct

    The Project Manager must escalate via an Exception Report.

  • Continue with the plan and report the overrun in the next Highlight Report.

    Why it's wrong here

    Continuing without escalation violates management by exception.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.