Which process is used by the Project Manager to authorize work for a Team Manager?

⚠ Common exam trap

Test-takers frequently confuse the Project Manager's authorization activity in 'Controlling a Stage' with the Team Manager's execution activity in 'Managing Product Delivery', leading candidates to select option A.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Controlling a Stage

In PRINCE2, the 'Controlling a Stage' process is used by the Project Manager to assign work to Team Managers and authorize Work Packages. This process includes the 'Authorize a Work Package' activity, which formally delegates the delivery of one or more products to a Team Manager. The other processes either occur before the stage is underway or are performed at the management level above the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Managing Product Delivery

    Why it's wrong here

    Managing Product Delivery is the Team Manager's process for accepting, executing and delivering a work package; the Project Manager does not authorise work there. It tempts because work packages are central to it, but the authorisation itself is issued from Controlling a Stage.

  • ✓

    Controlling a Stage

    Why this is correct

    Controlling a Stage is where the Project Manager authorises work packages, delegating agreed products and tolerances to Team Managers. Work authorisation occurs at stage level, not during Initiating a Project or Managing Product Delivery, which receives rather than grants that authority.

  • ✗

    Starting Up a Project

    Why it's wrong here

    Starting Up a Project covers the pre-project activities that produce the project brief and appoint the project board; it issues no work authorisation to a Team Manager. It tempts as the earliest process where the Project Manager is active, but authorising work packages belongs to Controlling a Stage.

  • ✗

    Directing a Project

    Why it's wrong here

    Directing a Project is the project board's process for decision-making and overall direction, not the Project Manager's route for issuing work packages. It tempts because it authorises the project itself, but the Project Manager authorises a Team Manager's work through Controlling a Stage.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.